Causes of Time Overrun in Construction of Building Projects in Pakistan

Authors

  • F. A. Soomro Department of Civil Engineering, Mehran University, Pakistan
  • M. J. Memon Department of Civil Engineering, Mehran University, Pakistan
  • A. F. Chandio Department of Electronics Engineering, Quaid-e-Awam University of Engineering, Science & Technology, Pakistan
  • S. Sohu Department of Civil Engineering, Quaid-e-Awam University College of Engineering, Science & Technology, Pakistan
  • R. Soomro Faculty of Civil Engineering, Universiti Teknologi Malaysia, Malaysia
Volume: 9 | Issue: 1 | Pages: 3762-3764 | February 2019 | https://doi.org/10.48084/etasr.2449

Abstract

Time overrun in construction projects is a very serious issue in developed countries. The main object of this research is to find the main causes of time overrun in the construction of building project and its possible mitigation measures. Quantitative approach was adopted in this research to achieve object and RIW (relative importance weight) approach was used for collecting data. Financial issues faced by the contractor, contractor’s inexperience, weather impacts, late delivery of material, mistakes in design, shortage of skilled labor, incompetent subcontractor and mistakes in time estimation were identified as main causes of time overrun in construction projects and possible mitigation measures were also proposed from experts. This research will help in giving awareness to stakeholders to narrow down the factors of time overrun in construction projects in Pakistan.

Keywords:

time overrun, causes, building projects, mitigation measures, Pakistan

Downloads

Download data is not yet available.

References

R. F. Aziz, A. A. Abdel-Hakam, “Exploring delay causes of road construction projects in Egypt”, Alexandria Engineering Journal, Vol. 2, No. 5, pp. 16-23, 2016 DOI: https://doi.org/10.1016/j.aej.2016.03.006

M. Y. Honrao, D. B. Desai, “Study of delay in execution of infrastructure projects–highway construction”, International Journal of Scientific and Research Publications, Vol. 5, No. 6, pp. 1-8, 2015

G. Kikwasi, “Causes and effects of delays and disruptions in construction projects in Tanzania”, Australasian Journal of Construction Economics and Building-Conference Series, Vol. 1, No. 2, pp. 52-59, 2013 DOI: https://doi.org/10.5130/ajceb-cs.v1i2.3166

M. Tafazzoli, Dynamic Risk Analysis of Construction Delays Using Fuzzy-Failure Mode Effects Analysis, PhD Thesis, University of Nevada, USA, 2017

Y. A. Olawale, M. Sun, “Cost and time control of construction projects: inhibiting factors and mitigating measures in practice”, Construction Management and Economics, Vol. 28, No. 5, pp. 509-526, 2010 DOI: https://doi.org/10.1080/01446191003674519

H. M. P. Moura, J. M. C. Teixeira, B. Pires, “Dealing with cost and time in the portuguese construction industry”, CIB World Building Congress, Cape Town, South Africa, May 14-17, 2007

O. Duran, Current Risk Management Applications in Turkish Construction Industry, MSc Thesis, University of Gaziantep, Turkey, 2006

C. T. Amoatey, Y. A. Ameyaw, E. Adaku, S. Famiyeh, “Analysing delay causes and effects in Ghanaian state housing construction projects”, International Journal of Managing Projects in Business, Vol. 8, No. 1, pp. 198-214, 2015 DOI: https://doi.org/10.1108/IJMPB-04-2014-0035

S. Haq, Y. Rashid, M. S. Aslam, “Effects of delay in construction projects of Punjub-Pakistan: An emperical study”, Journal of Basic and Applied Scientific Research, Vol. 4, No. 4, pp. 98-104, 2014

S. Sohu, N. A. Memon, S. A. Abbasi, M. A. Pahore, K. Ullah, “Causes of Delay in Highway Projects in Pakistan”, 8th International Civil Engineering Congress, Karachi, Pakistan, December 23-24, 2016

Z. K. Bangash, “Analyzing the Causes of Delays in Construction Projects for Peshawar: Contractor Perception”, Journal of Emerging Trends in Applied Engineering, Vol. 1, No. 3, pp. 12-18, 2016

F. D. K. Fugar, A. B. Agyakwah-Baah, “Delays in building construction projects in Ghana”, Australasian Journal of Construction Economics and Building, Vol. 10, No. 1-2, pp. 103-116, 2010 DOI: https://doi.org/10.5130/ajceb.v10i1/2.1592

D. W. M. Chan, M. M. Kumaraswamy, “Reasons for delay in civil engineering projects - The case of Hong Kong”, Transactions, Vol. 2, No. 3, pp. 1–8, 1996 DOI: https://doi.org/10.1080/1023697X.1995.10667685

N. R. Mansfield, O. Ugwu, T. Doran, “Causes of delay and cost overruns in Nigerian, Construction project”, International Journal of Project Management, Vol. 12, No. 4, pp. 254-260, 1994 DOI: https://doi.org/10.1016/0263-7863(94)90050-7

D. O. Ogeno, Factors Influencing Completion of Construction Projects in Kenya: A case of Government Buildings Construction Projects in Nairobi County, Kenya, MSc Thesis, University of Nairobi, Kenya, 2016

H. Emam, P. Farrell, M. Abdelaal,“Causes of delay on infrastructure projects in Qatar”, 31st Annual ARCOM Conference, Lincoln, UK, September 7-9, 2015

L. Le-Hoai, Y. D. Lee, J. Y. Lee, “Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries”, KSCE Journal of Civil Engineering, Vol. 12, No. 6, pp. 367-377, 2008 DOI: https://doi.org/10.1007/s12205-008-0367-7

G. Ballard, L. Koskela, G. Howell, T. Zabelle,“Production System Design in Construction”, 9th Annual Conference of International Group for Lean Construction, Singapore, August 6-8, 2001

Y. Frimpong, J. Oluwoye, “Significant Factors Causing Delay and Cost Overruns in Construction of Groundwater Projects in Ghana”, Journal of Construction Research, Vol. 4, No. 2, pp. 175-187 2003 DOI: https://doi.org/10.1142/S1609945103000418

W. Alaghbari, M. R. A. Kadir, A. Salim, Ernawati, “The significant factors causing delay of building construction projects in Malaysia”. Engineering, Construction and Architectural Management, Vol. 14, No. 2, pp. 192-206, 2007 DOI: https://doi.org/10.1108/09699980710731308

A. H. Al-Momani, “Construction delay: a quantitative analysis”, International Journal of Project Management, Vol. 18, No. 1, pp. 51-59, 2000 DOI: https://doi.org/10.1016/S0263-7863(98)00060-X

A. S. Faridi, S. M. El-Sayegh,“Significant factors causing delay in the UAE construction industry”, Construction Management and Economics, Vol. 24, No. 11, pp. 1167-1176, 2006 DOI: https://doi.org/10.1080/01446190600827033

R. F. Aziz, “Ranking of delay factors in construction projects after Egyptian revolution”, Alexandria Engineering Journal, Vol. 52, No. 3, pp. 387-406, 2013 DOI: https://doi.org/10.1016/j.aej.2013.03.002

M. Sambasivan, Y. W. Soon, “Causes and effects of delays in Malaysian construction industry”, International Journal of Project Management, Vol. 25, No. 5, pp. 517-526, 2007 DOI: https://doi.org/10.1016/j.ijproman.2006.11.007

A. Senouci, A. Ismail, N. Eldin, “Time Delay and Cost Overrun in Qatari Public Construction Projects”, Procedia Engineering, Vol. 164, pp. 368-375, 2016 DOI: https://doi.org/10.1016/j.proeng.2016.11.632

G. Sweis, R. Sweis, A. A. Hammad, A. Shboul, “Delays in construction projects: The case of Jordan”, International Journal of Project Management, Vol. 26, No. 6, pp. 665-674, 2008 DOI: https://doi.org/10.1016/j.ijproman.2007.09.009

Downloads

How to Cite

[1]
Soomro, F.A., Memon, M.J., Chandio, A.F., Sohu, S. and Soomro, R. 2019. Causes of Time Overrun in Construction of Building Projects in Pakistan. Engineering, Technology & Applied Science Research. 9, 1 (Feb. 2019), 3762–3764. DOI:https://doi.org/10.48084/etasr.2449.

Metrics

Abstract Views: 5682
PDF Downloads: 1032

Metrics Information

Most read articles by the same author(s)

1 2 > >>