A Mathematical Model to Predict Optimal Risk Response Budget using Genetic Algorithm
Received: 23 March 2024 | Revised: 11 April 2024 | Accepted: 17 April 2024 | Online: 1 June 2024
Corresponding author: Hiba Omer Ghaeb Aljorany
Abstract
Construction projects encounter a variety of risks, which require a thorough risk response phase to identify, evaluate, and determine solutions. This study presents a methodology for effectively choosing an appropriate risk response strategy and allocating suitable funds for the risk response phase of building projects. The framework employs optimization approaches and evolutionary principles, specifically utilizing the Genetic Algorithm technique. The objective of the model is to reduce costs and determine a suitable fund allocation strategy with minimum risk. The effectiveness of the framework is assessed in an actual building project involving a ventilation and air conditioning system, demonstrating its ability to optimize risk response and assist decision-makers in making well-informed choices.
Keywords:
risk management, risk response, optimization model, genetic algorithmDownloads
References
M. Fan, N.-P. Lin, and C. Sheu, "Choosing a project risk-handling strategy: An analytical model," International Journal of Production Economics, vol. 112, no. 2, pp. 700–713, Apr. 2008. DOI: https://doi.org/10.1016/j.ijpe.2007.06.006
A. M. Burhan, Risk management in construction projects. Baghdad, Iraq: University of Baghdad, 2003.
E. K. Rasheed, "Development of a Blueprint Impact System of the risks on construction projects Implementation," Journal of Engineering, vol. 21, no. 8, pp. 28–49, Aug. 2015. DOI: https://doi.org/10.31026/j.eng.2015.08.12
H. O. Ghaeb and A. M. R. Mahjoob, "Risk Response in Construction Project: A Review Study," Journal of Engineering, vol. 29, no. 8, pp. 121–137, Aug. 2023. DOI: https://doi.org/10.31026/j.eng.2023.08.09
A. A. Alfahad and A. M. Burhan, "BIM-Supporting System by Integrating Risk Management and Value Management," Engineering, Technology & Applied Science Research, vol. 13, no. 6, pp. 12130–12137, Dec. 2023. DOI: https://doi.org/10.48084/etasr.6427
H. E. Hossny, A. H. Ibrahim, and A. Elnady, "Assessment of Construction Project Complexity," The Open Civil Engineering Journal, vol. 15, no. 1, pp. 414–423, Dec. 2021. DOI: https://doi.org/10.2174/1874149502115010414
R. J. K. Jalhoom and A. M. R. Mahjoob, "An Extensive Literature Review on Risk Assessment Models (Techniques and Methodology) for Construction Industry," Journal of Engineering, vol. 29, no. 8, pp. 76–93, Aug. 2023. DOI: https://doi.org/10.31026/j.eng.2023.08.06
A. Alameri, A. S. A. M. Alhammadi, A. H. Memon, I. A. Rahman, and N. A. N. Nasaruddin, "Assessing the Risk Level of the Challenges Faced In Construction Projects," Engineering, Technology & Applied Science Research, vol. 11, no. 3, pp. 7152–7157, Jun. 2021. DOI: https://doi.org/10.48084/etasr.4020
T. Zayed, M. Amer, and J. Pan, "Assessing risk and uncertainty inherent in Chinese highway projects using AHP," International Journal of Project Management, vol. 26, no. 4, pp. 408–419, May 2008. DOI: https://doi.org/10.1016/j.ijproman.2007.05.012
E. K. Rasheed, "Valuation the Impact of Risks on the Goals and the Safety of Construction Projects in Iraq," Journal of Engineering, vol. 21, no. 4, pp. 1–19, Dec. 2015. DOI: https://doi.org/10.31026/j.eng.2015.04.10
A. D. Nandagavale and B. A. Konnur, "Risk Management in the Construction Project: Review," International Research Journal of Engineering and Technology, vol. 6, no. 4, pp. 4003–4006, 2019.
P. K. Jain and S. T. Qadri, "Identification of Risk in Construction Projects," International Research Journal of Engineering and Technology, vol. 7, no. 11, pp. 253–260, 2020.
S. H. N. Alani and A. M. R. Mahjoob, "Corruption Risk Analysis at the Project Planning Stage in the Iraqi Construction Sector using the Bowtie Methodology," Engineering, Technology & Applied Science Research, vol. 11, no. 3, pp. 7223–7227, Jun. 2021. DOI: https://doi.org/10.48084/etasr.4060
S. H. Fateminia, N. G. Seresht, and A. R. Fayek, "Evaluating Risk Response Strategies on Construction Projects Using a Fuzzy Rule-Based System," in 36th International Symposium on Automation and Robotics in Construction, Banff, AB, Canada, Dec. 2019, pp. 282–288. DOI: https://doi.org/10.22260/ISARC2019/0038
A. Nieto-Morote and F. Ruz-Vila, "A fuzzy approach to construction project risk assessment," International Journal of Project Management, vol. 29, no. 2, pp. 220–231, Feb. 2011. DOI: https://doi.org/10.1016/j.ijproman.2010.02.002
A. H. Beg and M. Z. Islam, "Advantages and limitations of genetic algorithms for clustering records," in 11th Conference on Industrial Electronics and Applications, Hefei, China, Jun. 2016, pp. 2478–2483. DOI: https://doi.org/10.1109/ICIEA.2016.7604009
V. Bhosale, D. S. S. Shastri, and M. A. Khandare, "A Review of Genetic Algorithm used for optimizing scheduling of Resource Constraint construction projects," International Research Journal of Engineering and Technology, vol. 4, no. 5, pp. 2869–2872, 2017.
A. B. Senouci and N. N. Eldin, "Use of Genetic Algorithms in Resource Scheduling of Construction Projects," Journal of Construction Engineering and Management, vol. 130, no. 6, pp. 869–877, Dec. 2004. DOI: https://doi.org/10.1061/(ASCE)0733-9364(2004)130:6(869)
S. N. Sivanandam and S. N. Deepa, Introduction to Genetic Algorithms. New York, NY, USA: Springer, 2008.
Y. Zhang and Z.-P. Fan, "An optimization method for selecting project risk response strategies," International Journal of Project Management, vol. 32, no. 3, pp. 412–422, Apr. 2014. DOI: https://doi.org/10.1016/j.ijproman.2013.06.006
M. Kilic, G. Ulusoy, and F. S. Serifoglu, "A bi-objective genetic algorithm approach to risk mitigation in project scheduling," International Journal of Production Economics, vol. 112, no. 1, pp. 202–216, Mar. 2008. DOI: https://doi.org/10.1016/j.ijpe.2006.08.027
C. Fang, F. Marle, M. Xie, and E. Zio, "An Integrated Framework for Risk Response Planning Under Resource Constraints in Large Engineering Projects," IEEE Transactions on Engineering Management, vol. 60, no. 3, pp. 627–639, Aug. 2013. DOI: https://doi.org/10.1109/TEM.2013.2242078
E. Cheraghi, M. Khalilzadeh, S. Shojaei, and S. Zohrehvandi, "A mathematical Model to select the Risk Response Strategies of the Construction Projects: Case Study of Saba Tower," Procedia Computer Science, vol. 121, pp. 609–616, Jan. 2017. DOI: https://doi.org/10.1016/j.procs.2017.11.080
H. Fukuda and H. Kuwano, "The Mathematical Model of Project Risk Responses in Project Risk Management," Journal of the Operations Research Society of Japan, vol. 60, no. 2, pp. 192–200, 2017. DOI: https://doi.org/10.15807/jorsj.60.192
R. Soofifard, M. Bafruei, and M. Gharib, "A Mathematical model for selecting the project risk responses in construction projects," International Journal of Optimization in Civil Engineering, vol. 8, no. 4, pp. 601–624, Jan. 2018.
A. Ghassemi and A. Darvishpour, "A novel approach for risk evaluation and risk response planning in a geothermal drilling project using DEMATEL and fuzzy ANP," Decision Science Letters, vol. 7, no. 3, pp. 225–242, 2018. DOI: https://doi.org/10.5267/j.dsl.2017.10.001
S. Shoar and A. Nazari, "An optimization framework for risk response actions selection using hybrid ACO and FTOPSIS," Scientia Iranica, vol. 26, no. 3, pp. 1763–1777, Jun. 2019.
A. A. Mahmoud al-Mukahal, "Risk Management of Construction Projects," Engineering Management Research, vol. 9, no. 1, pp. 15–27, May 2020. DOI: https://doi.org/10.5539/emr.v9n1p15
W. Bransah, "Discovering Project Risk Management Practices in Construction Industry of Ghana," Dama Academic Scholarly Journal of Researchers, vol. 5, no. 3, pp. 1–14, 2020.
N. H. Kadum, "The integration of Risk management and BIM to Manage the duration of construction projects," M.S. thesis, University of Diyala, Baqubah, DI, Iraq, 2021.
M. Singh, S. Deep, and R. Banerjee, "Risk management in construction projects as per Indian scenario," International Journal of Civil Engineering and Technology, vol. 8, no. 3, pp. 127–136, Mar. 2017.
I. Ben-David and T. Raz, "An integrated approach for risk response development in project planning," Journal of the Operational Research Society, vol. 52, no. 1, pp. 14–25, Jan. 2001. DOI: https://doi.org/10.1057/palgrave.jors.2601029
Downloads
How to Cite
License
Copyright (c) 2024 Hiba Omer Ghaeb Aljorany, Ahmed Mohammed Raoof Mahjoob
This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain the copyright and grant the journal the right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) after its publication in ETASR with an acknowledgement of its initial publication in this journal.