Building Information Modelling (BIM) as an Efficient Solution to Middle Eastern Construction Project Delays
Received: 9 August 2024 | Revised: 25 October 2024 | Accepted: 23 November 2024 | Online: 2 February 2025
Corresponding author: Shakir Al-Busaltan
Abstract
The construction and building industry is considered one of the essential players in the economic sector that contributes significantly to creating jobs and generating financial resources. This study provides a review of the construction industry's capability available in the Middle Eastern countries, the development process, and its importance for the economic growth. It analyzes what causes construction projects to go over budget and behind schedule in an attempt to draw conclusions that can be applied to a broader body of research. Delays are costly in terms of time, money, quality, and safety. Some adverse outcomes of project delays are disputes between employer and contractor, lower revenue and productivity, and incomplete projects. This research investigates the reasons behind the construction setbacks in the Middle East and what can be done to rectify the situation. Moreover, it examines the Building Information Modeling (BIM) as a tool to reduce the construction delays. The BIM permits the digital construction of facilities before their physical structure, which aids in time management, reduces risks, improves security, and resolves problems.
Keywords:
construction industry, building industry, delays, Building Information Modeling (BIM)Downloads
References
H. Emam, M. Abdelaal, and P. Farell, "Causes of delay in GCC construction projects: A Critical Review," in 1st International Conference on Smart, Sustainable and Healthy Cities [CIB-MENA], Abu Dhabi, UAE, Dec. 2014, pp. 607–621.
R. F. M. Ameen, "Evaluation of the sustainability of the urban development sector in Iraq," IOP Conference Series: Materials Science and Engineering, vol. 1067, no. 1, Oct. 2021, Art. no. 012064.
S. A. Assaf and S. Al-Hejji, "Causes of delay in large construction projects," International Journal of Project Management, vol. 24, no. 4, pp. 349–357, May 2006.
A. M. Jarkas and J. H. Younes, "Principle Factors Contributing to Construction Delays in the State of Qatar," International Journal of Construction Project Management, vol. 6, no. 1, pp. 39–62, 2014.
R. F. M. Ameen, S. S. Shalal, and S. J. K. Almayyahi, "The effect of urban form factors and social sustainability on the shaping of traditional religious cities: An Iraqi case study," AIP Conference Proceedings, vol. 2631, no. 1, May 2023, Art. no. 060001.
M. A. O. Mydin, N. M. Sani, N. A. A. Salim, and N. M. Alias, "Assessment of Influential Causes of Construction Project Delay in Malaysian Private Housing from Developer’s Viewpoint," E3S Web of Conferences, vol. 3, 2014, Art. no. 01027.
Y. Arayici, C. Egbu, and P. Coates, "Building information modelling (BIM) implementation and remote construction projects: Issues, Challenges and Critiques," Journal of Information Technology in Construction (ITcon), vol. 17, no. 5, pp. 75–92, May 2012.
C. Eastman, P. Teicholz, R. Sacks, and K. Liston, BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors, 2nd edition. Hoboken, NJ: John Wiley & Sons Inc, 2011.
T. Goubau, "What is BIM? What are its Benefits to the Construction Industry?," Medium, Dec. 01, 2016.
R. F. M. Ameen and M. Mourshed, "Environmental, Social and Economic Challenges for Urban Development: Stakeholder’s Perception in a Developing Economy," in The 16th International Conference on Computing in Civil and Building Engineering 2016, ICCCBE2016, Osaka, Japan, Jul. 2016.
V. Kushwaha, "Contribution Of Building Information Modeling (BIM) To Solve Problems In Architecture, Engineering and Construction (AEC) Industry and Addressing Barriers to Implementation of BIM," International Research Journal of Engineering and Technology (IRJET), vol. 03, no. 01, Jan. 2016.
S. Azhar, "Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry," Leadership and Management in Engineering, vol. 11, no. 3, pp. 241–252, Jul. 2011.
A. Enshassi and L. Ahmed AbuHamra, "An investigation of building information modelling functions in the Palestinian construction industry," Revista ingeniería de construcción, vol. 31, no. 2, pp. 127–138, Aug. 2016.
W. A. Hatem, A. M. Abd, and N. N. Abbas, "Motivation Factors for Adopting Building Information Modeling (BIM) in Iraq," Engineering, Technology & Applied Science Research, vol. 8, no. 2, pp. 2668–2672, Apr. 2018.
C. Hajj, "Integrating Building Information Modeling in the Construction Sector: The Middle East and North Africa Case," Doctoral thesis, Universidad de Granada, 2022.
S. Liu, B. Xie, L. Tivendal, and C. Liu, "Critical Barriers to BIM Implementation in the AEC Industry," International Journal of Marketing Studies, vol. 7, no. 6, Nov. 2015, Art. no. 162.
S. Kalinichuk, "Building Information Modeling Comprehensive Overview," Journal of Systems Integration, vol. 6, no. 3, pp. 25–34, 2015.
R. Hasan, S. M. A. Suliman, and Y. A. Malki, "An Investigation into the Delays in Road Projects in Bahrain," International Journal of Research in Engineering and Science (IJRES), vol. 2, no. 2, pp. 38–47, Feb. 2014.
M. E. Abd El-Razek, H. A. Bassioni, and A. M. Mobarak, "Causes of Delay in Building Construction Projects in Egypt," Journal of Construction Engineering and Management, vol. 134, no. 11, pp. 831–841, Nov. 2008.
T. Pourrostam and A. Ismail, "Significant Factors Causing and Effects of Delay in Iranian Construction Projects," Australian Journal of Basic and Applied Sciences, vol. 5, no. 7, pp. 450–456, 2011.
A. H. Al-Momani, "Construction delay: a quantitative analysis," International Journal of Project Management, vol. 18, no. 1, pp. 51–59, Feb. 2000.
M. I. Al-Khalil and M. A. Al-Ghafly, "Delay in public utility projects in Saudi Arabia," International Journal of Project Management, vol. 17, no. 2, pp. 101–106, Apr. 1999.
A. Al‐Kharashi and M. Skitmore, "Causes of delays in Saudi Arabian public sector construction projects," Construction Management and Economics, vol. 27, no. 1, pp. 3–23, Jan. 2009.
A. Albogamy, D. Scott, and N. Dawood, "Addressing Construction Delays in the Kingdom of Saudi Arabia," International Proceedings of Economics Development & Research, vol. 45, pp. 148–153, 2012.
S. A. Assaf, M. Al-Khalil, and M. Al-Hazmi, "Causes of Delay in Large Building Construction Projects," Journal of Management in Engineering, vol. 11, no. 2, pp. 45–50, Mar. 1995.
I. Mahamid, "Contributors to Schedule Delays in Public Construction Projects in Saudi Arabia: Owners’ Perspective," Journal of Construction Project Management and Innovation, vol. 3, no. 2, pp. 608–619, Dec. 2013.
A. Shash, "Delays in Gas, Oil, and Water Wells Projects," in AACE’s 56th Annual Meeting: A Fiesta for Total Cost Management, San Antonio, TX, USA, 2015.
M. Sami Ur Rehman, M. J. Thaheem, A. R. Nasir, and K. I. A. Khan, "Project schedule risk management through building information modelling," International Journal of Construction Management, vol. 22, no. 8, pp. 1489–1499, May 2022.
P. A. Koushki, K. Al‐Rashid, and N. Kartam, "Delays and cost increases in the construction of private residential projects in Kuwait," Construction Management and Economics, vol. 23, no. 3, pp. 285–294, Mar. 2005.
H. M. A. Tabtabai, "Causes for Delays in Construction Projects in Kuwait," Engineering Journal of the University of Qatar, vol. 15, pp. 19–37, 2002.
T. M. Mezher and W. Tawil, "Causes of delays in the construction industry in Lebanon," Engineering, Construction and Architectural Management, vol. 5, no. 3, pp. 252–260, Jan. 1998.
D. A. Shibani, M. Ghostin, D. Hassan, M. Saidani, and A. Agha, "Exploring the Impact of Implementing Building Information Modelling to Support Sustainable Development in the Lebanese Construction Industry: A Qualitative Approach," IJRDO - Journal of Mechanical And Civil Engineering, vol. 7, no. 1, pp. 33–62, Feb. 2021.
A. S. Alnuaimi and M. A. A. Mohsin, "Causes of Delay in Completion of Construction Projects in Oman," in International Conference on Innovations in Engineering and Technology (ICIET’2013), Bangkok, Thailand, Dec. 2013, pp. 267–270.
M. Ruqaishi and H. A. Bashir, "Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf Cooperation Council Countries: A Case Study," Journal of Management in Engineering, vol. 31, no. 3, May 2015, Art. no. 05014017.
N. A. Jurf and S. Beheiry, "Qatar residential construction projects," in 2010 Second International Conference on Engineering System Management and Applications, Sharjah, United Arab Emirates, Mar. 2010, pp. 1–6.
M. Gunduz, Y. Nielsen, and M. Ozdemir, "Fuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects," Journal of Management in Engineering, vol. 31, no. 4, Jul. 2015, Art. no. 04014055.
A. S. Faridi and S. M. El‐Sayegh, "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, vol. 24, no. 11, pp. 1167–1176, Nov. 2006.
M. A. Halloum and A. Bajracharya, "Cost and Time Overrun Revisited: A Study on the Infrastructure Construction Projects in Abu Dhabi, UAE," in Third International Conference on Construction in Developing Countries (ICCIDC–III), Bangkok, Thailand, Jul. 2012.
O. Motaleb and M. Kishk, “An Investigation into Causes and Effects of Construction Delays in UAE,” in Proceedings of the 26th Annual ARCOM Conference, Leeds, UK, Sep. 2010, pp. 1149–1157.
Z. Ren, M. Atout, and Jones, "Root Causes of Construction Project Delays in Dubai," in Proceedings of the 24th Annual ARCOM Conference, Cardiff, UK, Sep. 2008, pp. 749–757.
M. Salama, M. A. El Hamid, and B. Keogh, "Investigating the causes of delay within Oil and Gas projects in the U.A.E.," in 24th Annual Conference of Association of Researchers in Construction Management, Cardiff, United Kingdom, 2008, vol. 2, pp. 819–827.
O. I. Olanrewaju, A. F. Kineber, N. Chileshe, and D. J. Edwards, "Modelling the relationship between Building Information Modelling (BIM) implementation barriers, usage and awareness on building project lifecycle," Building and Environment, vol. 207, Jan. 2022, Art. no. 108556.
W. Wu and R. R. A. Issa, "BIM Education and Recruiting: Survey-Based Comparative Analysis of Issues, Perceptions, and Collaboration Opportunities," Journal of Professional Issues in Engineering Education and Practice, vol. 140, no. 2, Apr. 2014, Art. no. 04013014.
A. Malleson, "What’s going on in the world of BIM?: NBS National BIM Survey 2013," NBS, Jan. 11, 2012.
H. Yan and P. Demian, "Benefits and barriers of building information modelling," in 12th International Conference on Cumputing in Civil and Building Engineering, Beijing, China, 2008.
F. Khosrowshahi and Y. Arayici, "Roadmap for implementation of BIM in the UK construction industry," Engineering, Construction and Architectural Management, vol. 19, no. 6, pp. 610–635, Jan. 2012.
C. B. Tatum, "Classification System for Construction Technology," Journal of Construction Engineering and Management, vol. 114, no. 3, pp. 344–363, Sep. 1988.
R. Eadie, H. Odeyinka, M. Browne, C. Mahon, and M. Yohanis, "An Analysis of the Drivers for Adopting Building Information Modelling," Journal of Information Technology in Construction ITCON, vol. 18, pp. 338–352, Oct. 2013.
R. Eadie, M. Browne, H. Odeyinka, C. McKeown, and S. McNiff, "BIM implementation throughout the UK construction project lifecycle: An analysis," Automation in Construction, vol. 36, pp. 145–151, Dec. 2013.
D. Bryde, M. Broquetas, and J. M. Volm, "The project benefits of Building Information Modelling (BIM)," International Journal of Project Management, vol. 31, no. 7, pp. 971–980, Oct. 2013.
P. Biddix, "Mixed Methods Research Designs," Research Rundowns, Jul. 20, 2009.
D. F. Davis, S. L. Golicic, and C. N. Boerstler, "Benefits and challenges of conducting multiple methods research in marketing," Journal of the Academy of Marketing Science, vol. 39, no. 3, pp. 467–479, Jun. 2011.
Downloads
How to Cite
License
Copyright (c) 2024 Saba Jabbar Kadhuim Almayyahi, Raed Fawzi Mohammed Ameen, Shakir Al-Busaltan

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain the copyright and grant the journal the right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) after its publication in ETASR with an acknowledgement of its initial publication in this journal.