Influential Time and Cost Factors for Commercial Projects in the Malaysian Construction Industry

Authors

  • Samiullah Sohu Department of Civil Engineering, International Islamic University Malaysia, Malaysia | Department of Civil Engineering, The University of Larkano, Pakistan
  • Tahara Ramadzan Department of Civil Engineering, International Islamic University, Malaysia
  • Omar Shahid Khan Department of Civil and Architectural Engineering, University of Engineering and Technology Lahore, Pakistan
  • Sajjad Ahmed Bhatti Universiti Tun Hussein Onn Malaysia, Malaysia
  • Arslan Ahmed Sohoo Universiti Tun Hussein Onn Malaysia, Malaysia
Volume: 14 | Issue: 3 | Pages: 14170-14174 | June 2024 | https://doi.org/10.48084/etasr.7037

Abstract

Time and cost play an important role in project completion for both developing and developed countries. This study aims to identify the critical factors that influence the time and cost of commercial projects in Malaysia. A detailed questionnaire survey was conducted with industry professionals, and the results were analyzed based on the survey responses. The average index method was used to determine critical factors based on responses from professionals. The critical factors that affect time are poor contract management, client fund shortages, late drawing submissions, land acquisition problems, and inadequate surveying before construction. The critical factors identified for cost are delayed client payments, shortage of skilled workers, design changes, errors in the construction process, and changes in top management. This study raises awareness by identifying critical factors to minimize their impact so that construction can be completed on time and according to the defined budget, and maximize the benefits of future projects.

Keywords:

time, cost, experience, construction, critical factors, project, Malaysia

Downloads

Download data is not yet available.

References

M. A. Akhund, H. U. Imad, N. A. Memon, F. Siddiqui, A. R. Khoso, and A. A. Panhwar, "Contributing Factors of Time Overrun in Public Sector Construction Projects," Engineering, Technology & Applied Science Research, vol. 8, no. 5, pp. 3369–3372, Oct. 2018. DOI: https://doi.org/10.48084/etasr.2276

H. P. Moura, J. C. Teixeira, and B. Pires, "Dealing With Cost and Time in the Portuguese Construction Industry," presented at the CIB World Building Congress, 2007.

Z. Shehu, I. R. Endut, A. Akintoye, and G. D. Holt, "Cost overrun in the Malaysian construction industry projects: A deeper insight," International Journal of Project Management, vol. 32, no. 8, pp. 1471–1480, Nov. 2014. DOI: https://doi.org/10.1016/j.ijproman.2014.04.004

A. H. Memon, I. A. Rahman, M. R. Abdullah, and A. A. A. Azis, "Factors Affecting Construction Cost in Mara Large Construction Project: Perspective of Project Management Consultant," International Journal of Sustainable Construction Engineering and Technology, vol. 1, no. 2, pp. 41–54, 2010. DOI: https://doi.org/10.22452/jscp.vol2no1.4

K. M. M. El-Dash, O. M. O. Ramadan, and W. M. M. A. Youssef, "Duration Prediction Models for Construction Projects in Middle East," Engineering, Technology & Applied Science Research, vol. 9, no. 2, pp. 3924–3932, Apr. 2019. DOI: https://doi.org/10.48084/etasr.2531

D. W. M. Chan and M. M. Kumaraswam, "Reasons for Delay in Civil Engineering Projects – the Case of Hong Kong," HKIE Transactions, vol. 2, no. 3, pp. 1–8, Jan. 1995. DOI: https://doi.org/10.1080/1023697X.1995.10667685

A. Baghdadi and M. Kishk, "Saudi Arabian Aviation Construction Projects: Identification of Risks and Their Consequences," Procedia Engineering, vol. 123, pp. 32–40, Jan. 2015. DOI: https://doi.org/10.1016/j.proeng.2015.10.054

L. Le-Hoai, Y. D. Lee, and J. Y. Lee, "Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries," KSCE Journal of Civil Engineering, vol. 12, no. 6, pp. 367–377, Nov. 2008. DOI: https://doi.org/10.1007/s12205-008-0367-7

A. M. Alajmi and Z. Ahmed Memon, "A Review on Significant Factors Causing Delays in Saudi Arabia Construction Projects," Smart Cities, vol. 5, no. 4, pp. 1465–1487, Dec. 2022. DOI: https://doi.org/10.3390/smartcities5040075

F. A. Soomro, M. J. Memon, A. F. Chandio, S. Sohu, and R. Soomro, "Causes of Time Overrun in Construction of Building Projects in Pakistan," Engineering, Technology & Applied Science Research, vol. 9, no. 1, pp. 3762–3764, Feb. 2019. DOI: https://doi.org/10.48084/etasr.2449

S. M. E. Sepasgozar, M. A. Razkenari, and K. Barati, "The Importance of New Technology for Delay Mitigation in Construction Projects," American Journal of Civil Engineering and Architecture.

S. O. Ogunlana, K. Promkuntong, and V. Jearkjirm, "Construction delays in a fast-growing economy: Comparing Thailand with other economies," International Journal of Project Management, vol. 14, no. 1, pp. 37–45, Feb. 1996. DOI: https://doi.org/10.1016/0263-7863(95)00052-6

Y. Frimpong, J. Oluwoye, and L. Crawford, "Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study," International Journal of Project Management, vol. 21, no. 5, pp. 321–326, Jul. 2003. DOI: https://doi.org/10.1016/S0263-7863(02)00055-8

S. Sohu, A. F. Chandio, and K. Ullah, "Identification of Causes and Minimization of Delays in Highway Projects of Pakistan," Mehran University Research Journal of Engineering and Technology, vol. 38, no. 1, pp. 103–112, Jan. 2019. DOI: https://doi.org/10.22581/muet1982.1901.09

S. A. Assaf, M. Al-Khalil, and M. Al-Hazmi, "Causes of Delay in Large Building Construction Projects," Journal of Management in Engineering, vol. 11, no. 2, pp. 45–50, Mar. 1995. DOI: https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)

R. O. Asiedu and E. Adaku, "Cost overruns of public sector construction projects: a developing country perspective," International Journal of Managing Projects in Business, vol. 13, no. 1, pp. 66–84, Jan. 2019. DOI: https://doi.org/10.1108/IJMPB-09-2018-0177

C. D. Annamalaisami and A. Kuppuswamy, "Managing Cost Risks: Toward a Taxonomy of Cost Overrun Factors in Building Construction Projects," ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, vol. 7, no. 2, Jun. 2021, Art. no. 04021021. DOI: https://doi.org/10.1061/AJRUA6.0001132

S. Famiyeh, C. T. Amoatey, E. Adaku, and C. S. Agbenohevi, "Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana," Journal of Engineering, Design and Technology, vol. 15, no. 2, pp. 181–198, Jan. 2017. DOI: https://doi.org/10.1108/JEDT-11-2015-0075

S. Sohu, A. H. Abdullah, S. Nagapan, N. A. Memon, R. Yunus, and M. F. Hasmori, "Causative Factors of Cost Overrun in Building Projects of Pakistan," International Journal of Integrated Engineering, vol. 10, no. 9, 2018.

G. Heravi and M. Mohammadian, "Investigating cost overruns and delay in urban construction projects in Iran," International Journal of Construction Management, vol. 21, no. 9, pp. 958–968, Aug. 2021. DOI: https://doi.org/10.1080/15623599.2019.1601394

S. Durdyev, "Review of construction journals on causes of project cost overruns," Engineering, Construction and Architectural Management, vol. 28, no. 4, pp. 1241–1260, Jan. 2020. DOI: https://doi.org/10.1108/ECAM-02-2020-0137

R. O. Asiedu and C. Ameyaw, "A system dynamics approach to conceptualise causes of cost overrun of construction projects in developing countries," International Journal of Building Pathology and Adaptation, vol. 39, no. 5, pp. 831–851, Jan. 2020. DOI: https://doi.org/10.1108/IJBPA-05-2020-0043

S. Y. Kim, K. N. Tuan, J. D. Lee, H. Pham, and V. T. Luu, "Cost overrun factor analysis for hospital projects in Vietnam," KSCE Journal of Civil Engineering, vol. 22, no. 1, pp. 1–11, Jan. 2018. DOI: https://doi.org/10.1007/s12205-017-0947-5

Downloads

How to Cite

[1]
Sohu, S., Ramadzan, T., Khan, O.S., Bhatti, S.A. and Sohoo, A.A. 2024. Influential Time and Cost Factors for Commercial Projects in the Malaysian Construction Industry. Engineering, Technology & Applied Science Research. 14, 3 (Jun. 2024), 14170–14174. DOI:https://doi.org/10.48084/etasr.7037.