An Application of Analytic Network Process (ANP) to Assess Critical Risks of Bridge Projects in the Mekong Delta Region

Authors

  • Minh Duc Nguyen Faculty of Transport Economics, Ho Chi Minh City University of Transport, Vietnam
  • Phu Quang Tran Faculty of Transport Economics, Ho Chi Minh City University of Transport, Vietnam
  • Hoang Ba Nguyen Faculty of Transportation Engineering, Ho Chi Minh City University of Transport, Vietnam
Volume: 13 | Issue: 3 | Pages: 10622-10629 | June 2023 | https://doi.org/10.48084/etasr.5802

Abstract

Risk management is one of the critical factors contributing to infrastructure project success. Risk assessment enables both practitioners and decision-makers to identify and analyze potential risks and quantify risk impacts on project performance in terms of time, cost, and quality. Even though many studies attempt to investigate the risk of construction projects with the consideration of technical, organizational, and legal aspects, only a few studies deeply focus on identifying the critical risks of bridge projects with the examination of climate change impact. The current study concentrates on analyzing risks in bridge construction projects in the Mekong Delta region which has been significantly affected by climate change. An intensive review of previous publications and technical project reports from 2010 to 2021 was conducted to identify the list of potential risks and interviews and discussions with engineers and managers involved in bridge projects were carried out to identify critical risks of bridge projects. Analytic Network Process (ANP) method was introduced to evaluate the impact of such risks on the performance of bridge project implementation. The initial results of this study provide a holistic picture of risk management for bridge projects with the consideration of climate change impact. The findings can help the involved parties including owners, contractors, and project managers to assess particular risks and scheme backup plans to mitigate project delays and cost overruns.

Keywords:

risk assessment, risk management, bridge projects , Mekong Delta

Downloads

Download data is not yet available.

References

The Core Writing Team, R. K. Pachauri, and L. Meyer, Eds., Climate Change 2014: Synthesis Report. Contribution of Working Groups I, II and III to the Fifth Assessment Report of the Intergovernmental Panel on Climate Change. Geneva, Switzerland: IPCC, 2014.

J. H. M. Tah and V. Carr, "A proposal for construction project risk assessment using fuzzy logic," Construction Management and Economics, vol. 18, no. 4, pp. 491–500, Jun. 2000. DOI: https://doi.org/10.1080/01446190050024905

D. Skorupka, "Identification and Initial Risk Assessment of Construction Projects in Poland," Journal of Management in Engineering, vol. 24, no. 3, pp. 120–127, Jul. 2008. DOI: https://doi.org/10.1061/(ASCE)0742-597X(2008)24:3(120)

E. K. Zavadskas, Z. Turskis, and J. Tamosaitiene, "Risk assessment of construction projects," Journal of Civil Engineering and Management, vol. 16, no. 1, pp. 33–46, Jan. 2010.

A. Dziadosz and M. Rejment, "Risk Analysis in Construction Project - Chosen Methods," Procedia Engineering, vol. 122, pp. 258–265, Jan. 2015. DOI: https://doi.org/10.1016/j.proeng.2015.10.034

S. Iqbal, R. M. Choudhry, K. Holschemacher, A. Ali, and J. Tamosaitiene, "Risk management in construction projects," Technological and Economic Development of Economy, vol. 21, no. 1, pp. 65–78, Jan. 2015. DOI: https://doi.org/10.3846/20294913.2014.994582

K. Mhetre, B. A. Konnur, and A. B. Landage, "Risk Management in Construction Industry," International Journal of Engineering Research, vol. 5, no. 1, pp. 153–155, 2016.

R. M. Choudhry, M. A. Aslam, J. W. Hinze, and F. M. Arain, "Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines," Journal of Construction Engineering and Management, vol. 140, no. 7, Jul. 2014, Art. no. 04014020. DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000857

M. Tadayon, M. Jaafar, and E. Nasri, "An Assessment of Risk Identification in Large Construction Projects in Iran," Journal of Construction in Developing Countries, vol. 1, pp. 57–69, 2012.

N. B. Siraj and A. R. Fayek, "Risk Identification and Common Risks in Construction: Literature Review and Content Analysis," Journal of Construction Engineering and Management, vol. 145, no. 9, Sep. 2019. DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685

B. Flyvbjerg, "Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures," Environment and Planning B: Planning and Design, vol. 34, no. 4, pp. 578–597, Aug. 2007. DOI: https://doi.org/10.1068/b32111

S. Q. Wang, M. F. Dulaimi, and M. Y. Aguria, "Risk management framework for construction projects in developing countries," Construction Management and Economics, vol. 22, no. 3, pp. 237–252, Mar. 2004. DOI: https://doi.org/10.1080/0144619032000124689

"London Underground: Are the Public Private Partnerships likely to work successfully?," National Audit Office, London, UK, Jun. 2004.

S. Ahn, "A Case Study of the Risk Identification in Construction Project," Korean Journal of Construction Engineering and Management, vol. 16, no. 1, pp. 15–23, 2015. DOI: https://doi.org/10.6106/KJCEM.2015.16.1.015

D. Bajaj, J. Oluwoye, and D. Lenard, "An analysis of contractors’ approaches to risk identification in New South Wales, Australia," Construction Management and Economics, vol. 15, no. 4, pp. 363–369, Jul. 1997. DOI: https://doi.org/10.1080/014461997372917

O. Taylan, A. O. Bafail, R. M. S. Abdulaal, and M. R. Kabli, "Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies," Applied Soft Computing, vol. 17, pp. 105–116, Apr. 2014. DOI: https://doi.org/10.1016/j.asoc.2014.01.003

B.-G. Hwang, X. Zhao, and G. S. Yu, "Risk identification and allocation in underground rail construction joint ventures: contractors’ perspective," Journal of Civil Engineering and Management, vol. 22, no. 6, pp. 758–767, Aug. 2016. DOI: https://doi.org/10.3846/13923730.2014.914095

I. Manelele and M. Muya, "Risk identification on community‐based construction projects in Zambia," Journal of Engineering, Design and Technology, vol. 6, no. 2, pp. 145–161, Jan. 2008. DOI: https://doi.org/10.1108/17260530810891289

Y. Ke, S. Wang, A. P. C. Chan, and E. Cheung, "Understanding the risks in China’s PPP projects: ranking of their probability and consequence," Engineering, Construction and Architectural Management, vol. 18, no. 5, pp. 481–496, Jan. 2011. DOI: https://doi.org/10.1108/09699981111165176

P. X. W. Zou and G. Zhang, "Managing Risks in Construction Projects: Life Cycle and Stakeholder Perspectives," International Journal of Construction Management, vol. 9, no. 1, pp. 61–77, Jan. 2009. DOI: https://doi.org/10.1080/15623599.2009.10773122

R. J. Chapman, "The controlling influences on effective risk identification and assessment for construction design management," International Journal of Project Management, vol. 19, no. 3, pp. 147–160, Apr. 2001. DOI: https://doi.org/10.1016/S0263-7863(99)00070-8

N. N. Hlaing, D. Singh, R. L. K. Tiong, and M. Ehrlich, "Perceptions of Singapore construction contractors on construction risk identification," Journal of Financial Management of Property and Construction, vol. 13, no. 2, pp. 85–95, Jan. 2008. DOI: https://doi.org/10.1108/13664380810898104

C. A. L. Hilber and F. Robert-Nicoud, "On the origins of land use regulations: Theory and evidence from US metro areas," Journal of Urban Economics, vol. 75, pp. 29–43, May 2013. DOI: https://doi.org/10.1016/j.jue.2012.10.002

R. G. Funderburg, H. Nixon, M. G. Boarnet, and G. Ferguson, "New highways and land use change: Results from a quasi-experimental research design," Transportation Research Part A: Policy and Practice, vol. 44, no. 2, pp. 76–98, Feb. 2010. DOI: https://doi.org/10.1016/j.tra.2009.11.003

E. L. Glaeser and B. A. Ward, "The causes and consequences of land use regulation: Evidence from Greater Boston," Journal of Urban Economics, vol. 65, no. 3, pp. 265–278, May 2009. DOI: https://doi.org/10.1016/j.jue.2008.06.003

H. Alinaitwe, R. Apolot, and D. Tindiwensi, "Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects," Journal of Construction in Developing Countries, vol. 18, no. 2, pp. 33–47, 2013.

R. M. Fraser, "Compensation for extra preliminary and general (P & G) cost arising from delays, variations and disruptions: the palmiet pumped storage scheme," Tunnelling and Underground Space Technology, vol. 5, no. 3, pp. 205–216, Jan. 1990. DOI: https://doi.org/10.1016/0886-7798(90)90008-8

A. H. Al-Momani, "Construction delay: a quantitative analysis," International Journal of Project Management, vol. 18, no. 1, pp. 51–59, Feb. 2000. DOI: https://doi.org/10.1016/S0263-7863(98)00060-X

S. Ghosh and J. Jintanapakanont, "Identifying and assessing the critical risk factors in an underground rail project in Thailand: a factor analysis approach," International Journal of Project Management, vol. 22, no. 8, pp. 633–643, Nov. 2004. DOI: https://doi.org/10.1016/j.ijproman.2004.05.004

A. S. Akintoye and M. J. MacLeod, "Risk analysis and management in construction," International Journal of Project Management, vol. 15, no. 1, pp. 31–38, Feb. 1997. DOI: https://doi.org/10.1016/S0263-7863(96)00035-X

T. de Lemos, D. Eaton, M. Betts, and L. T. de Almeida, "Risk management in the Lusoponte concession—a case study of the two bridges in Lisbon, Portugal," International Journal of Project Management, vol. 22, no. 1, pp. 63–73, Jan. 2004. DOI: https://doi.org/10.1016/S0263-7863(03)00013-9

L. Bing, A. Akintoye, P. J. Edwards, and C. Hardcastle, "The allocation of risk in PPP/PFI construction projects in the UK," International Journal of Project Management, vol. 23, no. 1, pp. 25–35, Jan. 2005. DOI: https://doi.org/10.1016/j.ijproman.2004.04.006

R. Singh, Delays and Cost Overruns in Infrastructure Projects: An Enquiry into Extents, Causes and Remedies. New Delhi, India: University of Delhi, 2009.

R. Miller and D. R. Lessard, The Strategic Management of Large Engineering Projects: Shaping Institutions, Risks, and Governance. Cambridge, MA, United States: MIT Press, 2001. DOI: https://doi.org/10.7551/mitpress/6478.001.0001

T. Y. Lo, I. W. Fung, and K. C. Tung, "Construction Delays in Hong Kong Civil Engineering Projects," Journal of Construction Engineering and Management, vol. 132, no. 6, pp. 636–649, Jun. 2006. DOI: https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(636)

A. Nieto-Morote and F. Ruz-Vila, "A fuzzy approach to construction project risk assessment," International Journal of Project Management, vol. 29, no. 2, pp. 220–231, Feb. 2011. DOI: https://doi.org/10.1016/j.ijproman.2010.02.002

S. M. El-Sayegh, S. Manjikian, A. Ibrahim, A. Abouelyousr, and R. Jabbour, "Risk identification and assessment in sustainable construction projects in the UAE," International Journal of Construction Management, vol. 21, no. 4, pp. 327–336, Apr. 2021. DOI: https://doi.org/10.1080/15623599.2018.1536963

Y. Sun, D. Fang, S. Wang, M. Dai, and X. Lv, "Safety Risk Identification and Assessment for Beijing Olympic Venues Construction," Journal of Management in Engineering, vol. 24, no. 1, pp. 40–47, Jan. 2008. DOI: https://doi.org/10.1061/(ASCE)0742-597X(2008)24:1(40)

D. Kasap and M. Kaymak, "Risk Identification Step of the Project Risk Management," in Portland International Conference on Management of Engineering & Technology, Portland, OR, USA, Aug. 2007, pp. 2116–2120. DOI: https://doi.org/10.1109/PICMET.2007.4349543

M. Gunduz, Y. Nielsen, and M. Ozdemir, "Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey," Journal of Management in Engineering, vol. 29, no. 2, pp. 133–139, Apr. 2013. DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129

G. A. Hodge, "The risky business of public–private partnerships," Australian Journal of Public Administration, vol. 63, no. 4, pp. 37–49, 2004. DOI: https://doi.org/10.1111/j.1467-8500.2004.00400.x

M. Ebrat and R. Ghodsi, "Construction project risk assessment by using adaptive-network-based fuzzy inference system: An empirical study," KSCE Journal of Civil Engineering, vol. 18, no. 5, pp. 1213–1227, Jun. 2014. DOI: https://doi.org/10.1007/s12205-014-0139-5

G. Dehdasht, R. Mohamad Zin, M. S. Ferwati, M. Mohammed Abdullahi, A. Keyvanfar, and R. McCaffer, "DEMATEL-ANP Risk Assessment in Oil and Gas Construction Projects," Sustainability, vol. 9, no. 8, Aug. 2017, Art. no. 1420. DOI: https://doi.org/10.3390/su9081420

A. Taroun and J.-B. Yang, "A DST-based approach for construction project risk analysis," Journal of the Operational Research Society, vol. 64, no. 8, pp. 1221–1230, Aug. 2013. DOI: https://doi.org/10.1057/jors.2013.38

W. Haynes, "Transportation at the millennium: In search of a megaproject lens," Review of Policy Research, vol. 19, no. 2, pp. 62–64, 2002. DOI: https://doi.org/10.1111/j.1541-1338.2002.tb00265.x

M. Schieg, "Risk management in construction project management," Journal of Business Economics and Management, vol. 7, no. 2, pp. 77–83, Jan. 2006. DOI: https://doi.org/10.3846/16111699.2006.9636126

P. H. V. Nguyen and P. C. Nguyen, "Effects of Shaft Grouting on the Bearing Behavior of Barrette Piles: A Case Study in Ho Chi Minh City," Engineering, Technology & Applied Science Research, vol. 11, no. 5, pp. 7653–7657, Oct. 2021. DOI: https://doi.org/10.48084/etasr.4389

P. C. Nguyen, "Nonlinear Inelastic Earthquake Analysis of 2D Steel Frames," Engineering, Technology & Applied Science Research, vol. 10, no. 6, pp. 6393–6398, Dec. 2020. DOI: https://doi.org/10.48084/etasr.3855

P. C. Nguyen, "Local Instability Analysis for Axial Compressive Steel Columns," Engineering, Technology & Applied Science Research, vol. 12, no. 6, pp. 9527–9531, Dec. 2022. DOI: https://doi.org/10.48084/etasr.5238

S. M. H. Mojtahedi, S. M. Mousavi, and A. Makui, "Project risk identification and assessment simultaneously using multi-attribute group decision making technique," Safety Science, vol. 48, no. 4, pp. 499–507, Apr. 2010. DOI: https://doi.org/10.1016/j.ssci.2009.12.016

A. A. G. Hassanein and H. M. F. Afify, "A risk identification procedure for construction contracts—a case study of power station projects in Egypt," Civil Engineering and Environmental Systems, vol. 24, no. 1, pp. 3–14, Mar. 2007. DOI: https://doi.org/10.1080/10286600600910104

E. W. L. Cheng and H. Li, "Analytic Network Process Applied to Project Selection," Journal of Construction Engineering and Management, vol. 131, no. 4, pp. 459–466, Apr. 2005. DOI: https://doi.org/10.1061/(ASCE)0733-9364(2005)131:4(459)

T. L. Saaty, Theory and Applications of the Analytic Network Process: Decision Making With Benefits, Opportunities, Costs, and Risks. Pittsburgh, PA, USA: RWS Publications, 2005.

J. Pinto and D. Slevin, "Project success: Definitions and measurement techniques," Project Management Journal, vol. 2, pp. 67–72, Jan. 1988.

J. Gomes and M. Romao, "Improving Project Success: A Case Study Using Benefits and Project Management," Procedia Computer Science, vol. 100, pp. 489–497, Jan. 2016. DOI: https://doi.org/10.1016/j.procs.2016.09.187

S. Khosravi and H. Afshari, "A Success Measurement Model for Construction Projects," in International Conference on Financial Management and Economics, Hong Kong, China, Jul. 2011, pp. 186–190.

D. J. Bryde and L. Robinson, "Client versus contractor perspectives on project success criteria," International Journal of Project Management, vol. 23, no. 8, pp. 622–629, Nov. 2005. DOI: https://doi.org/10.1016/j.ijproman.2005.05.003

F. D. Bahia and J. R. de Farias Filho, "Analysis of success criteria in engineering, procurement and construction (EPC) projects," Revista de Gestao e Projetos, vol. 1, no. 2, pp. 49–67, 2010. DOI: https://doi.org/10.5585/gep.v1i2.15

A. Alameri, A. S. A. M. Alhammadi, A. H. Memon, I. A. Rahman, and N. a. N. Nasaruddin, "Assessing the Risk Level of the Challenges Faced In Construction Projects," Engineering, Technology & Applied Science Research, vol. 11, no. 3, pp. 7152–7157, Jun. 2021. DOI: https://doi.org/10.48084/etasr.4020

M. N. Sharabian, S. Ahmad, and M. Karakouzian, "Climate Change and Eutrophication: A Short Review," Engineering, Technology & Applied Science Research, vol. 8, no. 6, pp. 3668–3672, Dec. 2018. DOI: https://doi.org/10.48084/etasr.2392

P. T. Nguyen and P. C. Nguyen, "Risk Management in Engineering and Construction: A Case Study in Design-Build Projects in Vietnam," Engineering, Technology & Applied Science Research, vol. 10, no. 1, pp. 5237–5241, Feb. 2020. DOI: https://doi.org/10.48084/etasr.3286