A Comparative Analysis of the Construction Methods between Foreign and State-Owned Contractor Enterprises on the Jenelata Dam Project: The Case Study of Excavator Breaker and Blasting

Authors

  • M. Asad Abdurrahman Department of Civil Engineering, Universitas Hasanuddin, Gowa, Indonesia
  • Kasmiati Department of Civil Engineering, Universitas Hasanuddin, Gowa, Indonesia
  • Rusdi Usman Latief Department of Civil Engineering, Universitas Hasanuddin, Gowa, Indonesia
Volume: 15 | Issue: 6 | Pages: 29368-29376 | December 2025 | https://doi.org/10.48084/etasr.10936

Abstract

Determining the appropriate method and evaluating the work can have a significant impact on construction. Jenelata Dam is being constructed by both foreign and State-Owned Enterprise (SOE) contractors. Rock excavation is typically carried out using an excavator breaker or the blasting method. This study was conducted to compare the construction methods and to identify and evaluate the factors affecting the time performance of each method. This research uses descriptive, qualitative, and quantitative methods. A productivity analysis tool was utilized to compare the performance of the two contractors, and an analytical hierarchy process was deployed to determine the significance of the factors. Based on the evaluation results of the rock excavation work of the excavator breaker method at Concrete Face Rockfill Dam (CFRD) Works (left-bank), the daily productivity of SOE contractors is 729.10 m3/day for four units of equipment, and the completion time is 155 days. The daily productivity at the foreign contractor spillway is more effective using the blasting method of 875.95 m3/day for one unit of equipment, done in 73 days. According to both contractors, design is the most significant factor affecting construction time performance.

Keywords:

dam, rock excavation, excavator breaker, blasting

Downloads

Download data is not yet available.

References

Biro Komunikasi Publik Kementerian Pekerjaan Umum. "Penyedia Air untuk Daerah Irigasi Seluas 26.773 Ha, Pembangunan Bendungan Jenelata di Kabupaten Gowa Rampung Tahun 2028." https://pu.go.id/berita/penyedia-air-untuk-daerah-irigasi-seluas-26773-ha-pembangunan-bendungan-jenelata-di-kabupaten-gowa-rampung-tahun-2028

R. A. Wibowo and K. D. N. Putri, "Government Assignment of Contracts to State-owned Enterprises to Provide Infrastructure: Indonesia’s Experience," UUM Journal of Legal Studies, vol. 15, no. 2, pp. 675–705, July 2024. DOI: https://doi.org/10.32890/uumjls2024.15.2.11

A. P. Hadjar and F. Ardiyanto, "Laporan kerja praktek proyek pembangunan Bendungan Jlantah Karanganyar," Undergraduate report, Institut Teknologi Sepuluh Nopember (ITS), Surabaya, Indonesia, 2023.

R. Salhi, K. Messaoudi, and S. S. Boudemagh, "Identification of Factors Causing Delays in Construction Projects in Algeria," European Journal of Engineering and Formal Sciences, vol. 2, no. 1, pp. 6–11, Apr. 2018. DOI: https://doi.org/10.2478/ejef-2018-0001

M. R. Mustamin et al., "Risiko Keterlambatan Waktu pada Pelaksanaan Proyek Pembangunan Bendungan Pamukkulu dengan Metode Matriks Risiko dan Metode AHP," Jurnal Konstruksia, vol. 15, no. 1, pp. 145–158, Dec. 2023. DOI: https://doi.org/10.24853/jk.15.1.145-158

I. W. Styaningrum, D. Lydianingtias, and F. Purnomo, "Project Planning Spillway Pada Proyek Pembangunan Bendungan Bagong Kabupaten Trenggalek," JOS-MRK, vol. 3, no. 4, pp. 136–142, Dec. 2022.

D. Harusda, Syafrudin, and Silviana, "Pekerjaan Blasting sebagai Upaya Peningkatkan Kapasitas Produksi Pekerjaan Galian Tanah pada Proyek Jalan Tol Ruas Sigli-Banda Aceh," Jurnal Profesi Insinyur Indonesia, vol. 2, no. 2, pp. 99–103, Apr. 2024.

S. Choiriyah, F. Nuciferani, T. M. C. Agusdini, D. Kusumaningrum, and Y. Ilham, "Productivity Analysis of Heavy Equipment in the Nglurup Pond Project, Tulungagung Regency East Java Examined from Time and Cost Analysis," Proceedings of the 4th International Conference on Advanced Engineering and Technology, pp. 348–353, 2023. DOI: https://doi.org/10.5220/0012109600003680

A. L. Setiawan, L. A. R. Winanda, and V. Aditama, "Analisis Produktivitas Alat Berat Pada Pembangunan Bendungan Ameroro Kabupaten Konawe Sulawesi Tenggara," e-journal GELAGAR, vol. 2, no. 1, pp. 1–18, 2020.

R. N. N. Assyifa and B. Priyanto, "Analisis Produktivitas Alat Berat Untuk Pekerjaan Galian Pada Proyek Pembangunan Jalan Tepus-Jerukwudel II (STA 25+100-25+225)," Jurnal ISAINTEK, vol. 5, no. 4, pp. 19–23, 2022. DOI: https://doi.org/10.55606/isaintek.v5i02.59

T. Hadi, A. Nirmala, and Y. Herlambang, "Kajian Produktivitas Hydraulic Breaker Ecavator di Pt. Gilgal Batu Alam Lestari Kecamatan Sungai Kunyit Kabupaten Mempawah Provinsi Kalimantan Barat," Jurnal Teknik Kelautan, vol. 11, no. 3, 2024.

S. A. Aifudin, P. T. Juwono, and E. N. Cahya, "Studi Manajemen Konstruksi Proyek Rehabilitasi Spillway Bendungan Pacal Kab. Bojonegoro," Jurnal Teknologi dan Rekayasa Sumber Daya Air, vol. 4, no. 1, pp. 228–238, 2024. DOI: https://doi.org/10.21776/ub.jtresda.2024.004.01.019

W. V. Simamora, A. Naufal, W. Herwindo, and D. P. Riyanto, "Studi Evaluasi Manajemen Konstruksi Pekerjaan Galian Batu dengan Peledakan pada Bangunan Pelimpah Proyek Pembangunan Bendungan Budong-Budong," Jurnal Inovasi Konstruksi, vol. 3, no. 1, pp. 1–14, Apr. 2024. DOI: https://doi.org/10.56911/jik.v3i1.59

D. A. P. Pratomo, Suharyanto, and P. S. Atmojo, "Deformasi Bendungan Cirata berdasarkan Analisis Data Instrumen Patok Geser," Jurnal Teknik, vol. 19, no. 2, pp. 96–106, Dec. 2021. DOI: https://doi.org/10.37031/jt.v19i2.166

Y. A. Tanne and N. L. A. Indrayani, "Review of Construction Automation and Robotics Practices in Indonesian Construction State-Owned Enterprises: Position in Project Life Cycle, Gap to Best Practice and Potential Uses," Architecture, Structures and Construction, vol. 3, pp. 373–389, Sept. 2023. DOI: https://doi.org/10.1007/s44150-023-00098-5

T.-H. Le, D. Park, and C. Castillejos-Petalcorin, "Performance comparison of state-owned enterprises versus private firms in selected emerging Asian countries," Journal of Asian Business and Economic Studies, vol. 30, no. 1, pp. 26–48, Dec. 2021. DOI: https://doi.org/10.1108/JABES-08-2021-0116

D. Fei, "Networked Internationalization: Chinese Companies in Ethiopia’s Infrastructure Construction Sector," The Professional Geographer, vol. 73, no. 2, pp. 322–332, Apr. 2021. DOI: https://doi.org/10.1080/00330124.2020.1844572

K. Szarzec, W. Nowara, and B. Totleben, "State-owned enterprises as foreign direct investors: insights from EU countries," Post-Communist Economies, vol. 33, no. 5, pp. 517–540, July 2021. DOI: https://doi.org/10.1080/14631377.2020.1793603

B. Yang, "Following the state-owned enterprises: Chinese expatriate construction workers in Zambia," Asian and Pacific Migration Journal, vol. 30, no. 4, pp. 428–449. DOI: https://doi.org/10.1177/01171968211069726

H. Zong, G. Wang, and D. Cao, "Collaborative networks between contractors and subcontractors for infrastructure development: a comparative study of national quality award projects in China," Engineering, Construction and Architectural Management, vol. 32, no. 2, pp. 1074–1096, Sept. 2023. DOI: https://doi.org/10.1108/ECAM-05-2022-0442

W. Leutert, E. Plantan, and A. Strange, "Puzzling Partnerships: Overseas Infrastructure Development by Chinese State-Owned Enterprises and Humanitarian Organizations," Studies in Comparative International Development, vol. 58, pp. 195–223, June 2023. DOI: https://doi.org/10.1007/s12116-022-09368-7

Y. Niu, R. Zhang, G. Wu, and Q. Zhou, "Peer effects of internationalization for engineering news-record contractors: evidence from Chinese contractors," Engineering, Construction and Architectural Management, vol. 32, no. 1, pp. 454–482, July 2023. DOI: https://doi.org/10.1108/ECAM-10-2022-1002

W. K. Praja, "Factors Affecting the Effectiveness of Contractors’ All Risk Insurance Claims: A Study of State-Owned Contractors in Indonesia," Eduvest - Journal of Universal Studies, vol. 3, no. 9, pp. 1742–1753, Sept. 2023. DOI: https://doi.org/10.59188/eduvest.v3i9.907

Y. I. Silalahi, L. Masthura, and N. Fahriana, "Analisis Faktor - Faktor Penentu Keberhasilan Proyek Konstruksi Berdasarkan Mutu, Biaya dan Waktu," Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil, vol. 7, no. 2, pp. 233–240, Aug. 2023. DOI: https://doi.org/10.32832/komposit.v7i2.14240

Downloads

How to Cite

[1]
M. A. Abdurrahman, . Kasmiati, and R. U. Latief, “A Comparative Analysis of the Construction Methods between Foreign and State-Owned Contractor Enterprises on the Jenelata Dam Project: The Case Study of Excavator Breaker and Blasting”, Eng. Technol. Appl. Sci. Res., vol. 15, no. 6, pp. 29368–29376, Dec. 2025.

Metrics

Abstract Views: 222
PDF Downloads: 212

Metrics Information