A Comparative Analysis of the Construction Methods between Foreign and State-Owned Contractor Enterprises on the Jenelata Dam Project: The Case Study of Excavator Breaker and Blasting
Received: 13 March 2025 | Revised: 30 April 2025 and 28 July 2025 | Accepted: 1 August 2025 | Online: 21 October 2025
Corresponding author: M. Asad Abdurrahman
Abstract
Determining the appropriate method and evaluating the work can have a significant impact on construction. Jenelata Dam is being constructed by both foreign and State-Owned Enterprise (SOE) contractors. Rock excavation is typically carried out using an excavator breaker or the blasting method. This study was conducted to compare the construction methods and to identify and evaluate the factors affecting the time performance of each method. This research uses descriptive, qualitative, and quantitative methods. A productivity analysis tool was utilized to compare the performance of the two contractors, and an analytical hierarchy process was deployed to determine the significance of the factors. Based on the evaluation results of the rock excavation work of the excavator breaker method at Concrete Face Rockfill Dam (CFRD) Works (left-bank), the daily productivity of SOE contractors is 729.10 m3/day for four units of equipment, and the completion time is 155 days. The daily productivity at the foreign contractor spillway is more effective using the blasting method of 875.95 m3/day for one unit of equipment, done in 73 days. According to both contractors, design is the most significant factor affecting construction time performance.
Keywords:
dam, rock excavation, excavator breaker, blastingDownloads
References
Biro Komunikasi Publik Kementerian Pekerjaan Umum. "Penyedia Air untuk Daerah Irigasi Seluas 26.773 Ha, Pembangunan Bendungan Jenelata di Kabupaten Gowa Rampung Tahun 2028." https://pu.go.id/berita/penyedia-air-untuk-daerah-irigasi-seluas-26773-ha-pembangunan-bendungan-jenelata-di-kabupaten-gowa-rampung-tahun-2028
R. A. Wibowo and K. D. N. Putri, "Government Assignment of Contracts to State-owned Enterprises to Provide Infrastructure: Indonesia’s Experience," UUM Journal of Legal Studies, vol. 15, no. 2, pp. 675–705, July 2024. DOI: https://doi.org/10.32890/uumjls2024.15.2.11
A. P. Hadjar and F. Ardiyanto, "Laporan kerja praktek proyek pembangunan Bendungan Jlantah Karanganyar," Undergraduate report, Institut Teknologi Sepuluh Nopember (ITS), Surabaya, Indonesia, 2023.
R. Salhi, K. Messaoudi, and S. S. Boudemagh, "Identification of Factors Causing Delays in Construction Projects in Algeria," European Journal of Engineering and Formal Sciences, vol. 2, no. 1, pp. 6–11, Apr. 2018. DOI: https://doi.org/10.2478/ejef-2018-0001
M. R. Mustamin et al., "Risiko Keterlambatan Waktu pada Pelaksanaan Proyek Pembangunan Bendungan Pamukkulu dengan Metode Matriks Risiko dan Metode AHP," Jurnal Konstruksia, vol. 15, no. 1, pp. 145–158, Dec. 2023. DOI: https://doi.org/10.24853/jk.15.1.145-158
I. W. Styaningrum, D. Lydianingtias, and F. Purnomo, "Project Planning Spillway Pada Proyek Pembangunan Bendungan Bagong Kabupaten Trenggalek," JOS-MRK, vol. 3, no. 4, pp. 136–142, Dec. 2022.
D. Harusda, Syafrudin, and Silviana, "Pekerjaan Blasting sebagai Upaya Peningkatkan Kapasitas Produksi Pekerjaan Galian Tanah pada Proyek Jalan Tol Ruas Sigli-Banda Aceh," Jurnal Profesi Insinyur Indonesia, vol. 2, no. 2, pp. 99–103, Apr. 2024.
S. Choiriyah, F. Nuciferani, T. M. C. Agusdini, D. Kusumaningrum, and Y. Ilham, "Productivity Analysis of Heavy Equipment in the Nglurup Pond Project, Tulungagung Regency East Java Examined from Time and Cost Analysis," Proceedings of the 4th International Conference on Advanced Engineering and Technology, pp. 348–353, 2023. DOI: https://doi.org/10.5220/0012109600003680
A. L. Setiawan, L. A. R. Winanda, and V. Aditama, "Analisis Produktivitas Alat Berat Pada Pembangunan Bendungan Ameroro Kabupaten Konawe Sulawesi Tenggara," e-journal GELAGAR, vol. 2, no. 1, pp. 1–18, 2020.
R. N. N. Assyifa and B. Priyanto, "Analisis Produktivitas Alat Berat Untuk Pekerjaan Galian Pada Proyek Pembangunan Jalan Tepus-Jerukwudel II (STA 25+100-25+225)," Jurnal ISAINTEK, vol. 5, no. 4, pp. 19–23, 2022. DOI: https://doi.org/10.55606/isaintek.v5i02.59
T. Hadi, A. Nirmala, and Y. Herlambang, "Kajian Produktivitas Hydraulic Breaker Ecavator di Pt. Gilgal Batu Alam Lestari Kecamatan Sungai Kunyit Kabupaten Mempawah Provinsi Kalimantan Barat," Jurnal Teknik Kelautan, vol. 11, no. 3, 2024.
S. A. Aifudin, P. T. Juwono, and E. N. Cahya, "Studi Manajemen Konstruksi Proyek Rehabilitasi Spillway Bendungan Pacal Kab. Bojonegoro," Jurnal Teknologi dan Rekayasa Sumber Daya Air, vol. 4, no. 1, pp. 228–238, 2024. DOI: https://doi.org/10.21776/ub.jtresda.2024.004.01.019
W. V. Simamora, A. Naufal, W. Herwindo, and D. P. Riyanto, "Studi Evaluasi Manajemen Konstruksi Pekerjaan Galian Batu dengan Peledakan pada Bangunan Pelimpah Proyek Pembangunan Bendungan Budong-Budong," Jurnal Inovasi Konstruksi, vol. 3, no. 1, pp. 1–14, Apr. 2024. DOI: https://doi.org/10.56911/jik.v3i1.59
D. A. P. Pratomo, Suharyanto, and P. S. Atmojo, "Deformasi Bendungan Cirata berdasarkan Analisis Data Instrumen Patok Geser," Jurnal Teknik, vol. 19, no. 2, pp. 96–106, Dec. 2021. DOI: https://doi.org/10.37031/jt.v19i2.166
Y. A. Tanne and N. L. A. Indrayani, "Review of Construction Automation and Robotics Practices in Indonesian Construction State-Owned Enterprises: Position in Project Life Cycle, Gap to Best Practice and Potential Uses," Architecture, Structures and Construction, vol. 3, pp. 373–389, Sept. 2023. DOI: https://doi.org/10.1007/s44150-023-00098-5
T.-H. Le, D. Park, and C. Castillejos-Petalcorin, "Performance comparison of state-owned enterprises versus private firms in selected emerging Asian countries," Journal of Asian Business and Economic Studies, vol. 30, no. 1, pp. 26–48, Dec. 2021. DOI: https://doi.org/10.1108/JABES-08-2021-0116
D. Fei, "Networked Internationalization: Chinese Companies in Ethiopia’s Infrastructure Construction Sector," The Professional Geographer, vol. 73, no. 2, pp. 322–332, Apr. 2021. DOI: https://doi.org/10.1080/00330124.2020.1844572
K. Szarzec, W. Nowara, and B. Totleben, "State-owned enterprises as foreign direct investors: insights from EU countries," Post-Communist Economies, vol. 33, no. 5, pp. 517–540, July 2021. DOI: https://doi.org/10.1080/14631377.2020.1793603
B. Yang, "Following the state-owned enterprises: Chinese expatriate construction workers in Zambia," Asian and Pacific Migration Journal, vol. 30, no. 4, pp. 428–449. DOI: https://doi.org/10.1177/01171968211069726
H. Zong, G. Wang, and D. Cao, "Collaborative networks between contractors and subcontractors for infrastructure development: a comparative study of national quality award projects in China," Engineering, Construction and Architectural Management, vol. 32, no. 2, pp. 1074–1096, Sept. 2023. DOI: https://doi.org/10.1108/ECAM-05-2022-0442
W. Leutert, E. Plantan, and A. Strange, "Puzzling Partnerships: Overseas Infrastructure Development by Chinese State-Owned Enterprises and Humanitarian Organizations," Studies in Comparative International Development, vol. 58, pp. 195–223, June 2023. DOI: https://doi.org/10.1007/s12116-022-09368-7
Y. Niu, R. Zhang, G. Wu, and Q. Zhou, "Peer effects of internationalization for engineering news-record contractors: evidence from Chinese contractors," Engineering, Construction and Architectural Management, vol. 32, no. 1, pp. 454–482, July 2023. DOI: https://doi.org/10.1108/ECAM-10-2022-1002
W. K. Praja, "Factors Affecting the Effectiveness of Contractors’ All Risk Insurance Claims: A Study of State-Owned Contractors in Indonesia," Eduvest - Journal of Universal Studies, vol. 3, no. 9, pp. 1742–1753, Sept. 2023. DOI: https://doi.org/10.59188/eduvest.v3i9.907
Y. I. Silalahi, L. Masthura, and N. Fahriana, "Analisis Faktor - Faktor Penentu Keberhasilan Proyek Konstruksi Berdasarkan Mutu, Biaya dan Waktu," Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil, vol. 7, no. 2, pp. 233–240, Aug. 2023. DOI: https://doi.org/10.32832/komposit.v7i2.14240
Downloads
How to Cite
License
Copyright (c) 2025 M. Asad Abdurrahman, Kasmiati, Rusdi Usman Latief

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain the copyright and grant the journal the right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) after its publication in ETASR with an acknowledgement of its initial publication in this journal.