Using a Fuzzy Model to Evaluate Risks caused by Variation Orders in Construction Projects

Authors

  • Allam Abu Mwais Computer System Engineering Department, Faculty of Engineering, Arab American University, Palestine
  • Ibrahim Mahamid Civil Engineering Department, Faculty of Engineering, Arab American University, Palestine
Volume: 15 | Issue: 1 | Pages: 19030-19036 | February 2025 | https://doi.org/10.48084/etasr.8558

Abstract

The construction industry is the main driving sector for any country's economy. However, it is too risky due to the many risks and challenges in this industry. One of the main challenges in construction projects is variation orders, as they lead to conflicts between project parties and cause poor project performance. This study aims to evaluate the risks associated with variation orders in construction projects using fuzzy risk assessment. The targeted population is the construction contractors in Palestine. A questionnaire survey was used to collect data on the severity and frequency of the 22 identified factors of variation orders. Then, a fuzzy logic system was developed to rate these factors. The factor risk level was determined by connecting the relationship between the severity and frequency indices using If-Then rules. The determination of risk level is a critical task in the proposed fuzzy system, which depends on the complex combinations of all If-Then rules. Risk is determined not only by the If-Then rules but also by the weight of each rule. This study shows that the factors with the highest risk levels are scope change by the client, client financial problems, unavailability of required materials, poor design documents, and modification of specifications. The results can serve as guidelines for project participants who need to prepare and implement a comprehensive and effective risk management plan to meet project goals. To improve project performance, construction parties are recommended to implement the proposed method to assess risks related to construction projects. Finally, the proposed risk model demonstrates the ability to evaluate risk levels by aggregating rules and combining the project risk factors using a fuzzy logic model and MATLAB.

Keywords:

if-then, fuzzy logic, construction, variation, variation orders

Downloads

Download data is not yet available.

References

I. Mahamid, "Effect of change orders on rework in highway projects in Palestine," Journal of Financial Management of Property and Construction, vol. 22, no. 1, pp. 62–76, Jan. 2017.

I. Mahamid, "Study of relationship between rework and labor productivity in Building Construction Projects," Revista de la construcción, vol. 19, no. 1, pp. 30–40, Apr. 2020.

A. Enshassi, F. Arain, and S. Al‐Raee, "Causes of variation orders in construction projects in the Gaza Strip," Journal of Civil Engineering and Management, vol. 16, no. 4, pp. 540–551, Dec. 2010.

W. M. A. Khalifa and I. Mahamid, "Causes of Change Orders in Construction Projects," Engineering, Technology & Applied Science Research, vol. 9, no. 6, pp. 4956–4961, Dec. 2019.

M. Aslam, E. Baffoe-Twum, and F. Saleem, "Design Changes in Construction Projects – Causes and Impact on the Cost," Civil Engineering Journal, vol. 5, no. 7, pp. 1647–1655, Jul. 2019.

I. Mahamid, "Effects of Design Quality on Delay in Residential Construction Projects," Journal of Sustainable Architecture and Civil Engineering, vol. 28, no. 1, pp. 118–129, 2021.

A. R. Khoso, J. S. Khan, R. U. Faiz, and M. A. Akhund, "Assessment of Change Orders Attributes in Preconstruction and Construction Phase," Civil Engineering Journal, vol. 5, no. 3, pp. 616–623, Mar. 2019.

A. Alaryan, A. E. Emadelbeltagi, and M. Dawood, "Causes and effects of change orders on construction projects in Kuwait," International Journal of Engineering Research and Applications, vol. 4, no. 7, pp. 1–8, 2014.

K. K. Naji, M. Gunduz, and A. F. Naser, "The Effect of Change-Order Management Factors on Construction Project Success: A Structural Equation Modeling Approach," Journal of Construction Engineering and Management, vol. 148, no. 9, Sep. 2022, Art. no. 04022085.

E. Serag, A. Oloufa, L. Malone, and E. Radwan, "Model for Quantifying the Impact of Change Orders on Project Cost for U.S. Roadwork Construction," Journal of Construction Engineering and Management, vol. 136, no. 9, pp. 1015–1027, Sep. 2010.

M. P. Koirala and R. S. Shahi, "Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal," Evaluation and Program Planning, vol. 105, Aug. 2024, Art. no. 102436.

L. A. Zadeh, "Fuzzy sets," Information and Control, vol. 8, no. 3, pp. 338–353, Jun. 1965.

A. Nieto-Morote and F. Ruz-Vila, "A fuzzy approach to construction project risk assessment," International Journal of Project Management, vol. 29, no. 2, pp. 220–231, Feb. 2011.

Z. Osman, A. Omran, and C. K. Foo, "The potential effects of variation orders in construction projects," Journal of Engineering Annals of Faculty of Engineering Hunedoara, vol. VII, no. 2, pp. 141–152, 2009.

A. S. Alnuaimi, R. A. Taha, M. Al Mohsin, and A. S. Al-Harthi, "Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman," Journal of Construction Engineering and Management, vol. 136, no. 5, pp. 615–622, May 2010.

N. Homaid, A. Eldosouky, and M. AlGhmdi, "Change orders in Saudi linear construction projects," emirates Journal for engineering Research, vol. 16, no. 1, pp. 33–42, 2011.

D. Olsen, R. Killingsworth, and B. Page, "Change Order Causation; Who is the Guilty Party?," in 48th ASC Annual International Conference Proceedings, 2012.

M. Msallam, M. Abojaradeh, B. Jrew, and I. Zaki, "Controlling Of Variation Orders in Highway Projects in Jordan," Journal of Engineering and Architecture, vol. 3, no. 2, 2015.

I. Dikmen, M. T. Birgonul, and S. Han, "Using fuzzy risk assessment to rate cost overrun risk in international construction projects," International Journal of Project Management, vol. 25, no. 5, pp. 494–505, Jul. 2007.

H. Abd El Khalek, "Risk and Uncertainty Assessment Model in Construction Projects Using Fuzzy Logic," American Journal of Civil Engineering, vol. 4, no. 1, 2016, Art. no. 24.

A. A. Maamari and F. Khan, "Evaluating the Causes and Impact of Change Orders on Construction Projects Performance in Oman," International Journal of Research in Entrepreneurship & Business Studies, vol. 2, no. 1, pp. 41–50, Jan. 2021.

S. J. Alkhalifah, F. M. Tuffaha, L. A. Al Hadidi, and A. Ghaithan, "Factors influencing change orders in oil and gas construction projects in Saudi Arabia," Built Environment Project and Asset Management, vol. 13, no. 3, pp. 430–452, Jan. 2023.

A. R. Gheraba et al., "Causes, Effects, and Control Measures of Construction Change Orders in the U.S.," Journal of Civil Engineering and Architecture, vol. 17, no. 2, Feb. 2023.

C. T. Lin and Y. T. Chen, "Bid/no-bid decision-making – a fuzzy linguistic approach," International Journal of Project Management, vol. 22, no. 7, pp. 585–593, Oct. 2004.

H. H. Choi, H. N. Cho, and J. W. Seo, "Risk Assessment Methodology for Underground Construction Projects," Journal of Construction Engineering and Management, vol. 130, no. 2, pp. 258–272, Apr. 2004.

I. Mahamid, "Critical Factors Influencing the Bid / No-Bid Decision in the Palestinian Construction Industry," Engineering, Technology & Applied Science Research, vol. 12, no. 1, pp. 8096–8100, Feb. 2022.

C. W. Emory, Business Research Methods. Irwin, 1985.

I. Mahamid, "Risk matrix for factors affecting time delay in road construction projects: owners’ perspective," Engineering, Construction and Architectural Management, vol. 18, no. 6, pp. 609–617, Jan. 2011.