Identifying The Effective Factors for Cost Overrun and Time Delay in Water Construction Projects

Authors

  • D. Mirzai Matin Sharif University of Technology, International Campus Tehran, Iran
Volume: 6 | Issue: 4 | Pages: 1062-1066 | August 2016 | https://doi.org/10.48084/etasr.706

Abstract

Water construction projects in Iran frequently face problems which cause cost overrun and time delay, the two most common issues in construction projects in general. The objective of this survey is to identify and quantify these problems and thus help in avoiding them. This survey represents a collection of the most significant problems found in the literature, classified into 11 groups according to their source. The questionnaire form used contains 84 questions which were answered by random engineers who work in water construction projects. The Relative Importance Weight (RIW) method is used to weight the importance of each one of the 84 problems. The focus of this survey is on overall top ten issues which are: bureaucracy in bidding method, inflation, economical condition of the government, not enough information gathered and surveys done before design, monthly payment difficulties, material cost changes, law changes by the government, financial difficulties, mode of financing and payment for completed work and changes made by the owner. A section for each of these issues provides additional information about them. In the full text of this survey the same weighting method is used to classify the main groups, and the results show that issues related to the groups of government, owner and consultant has the most significant impact. The last part of this survey describes the point of view of the engineers who took part in this survey and the recommendations they made.

Keywords:

construction projects, water construction projects, Iran construction projects, time delay, cost overrun

Downloads

Download data is not yet available.

References

S. O. Ogunlana, P. O. Olomolaiye, “A survey of site management practice on some selected sites in Nigeria”, Building and Environment, Vol. 24, No. 2, pp.191-196, 1989 DOI: https://doi.org/10.1016/0360-1323(89)90009-7

Y. Frimpong, Project management in developing countries: causes of delay and cost overruns in construction of groundwater projects, Masters Research Project, University of Technology, Sydney, Australia. 2000

Y. Frimpong, J. Oluwoye, L. Crawford, “Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study”. International Journal of project management, Vol. 21, No. 5, pp. 321-326, 2003 DOI: https://doi.org/10.1016/S0263-7863(02)00055-8

M. I. Al-Khalil, A. A. Mohammed "Delay in public utility projects in Saudi Arabia." International Journal of Project Management, Vol. 17, No. 2, pp. 101-106, 1999 DOI: https://doi.org/10.1016/S0263-7863(98)00020-9

L. Le-Hoai, Y. Dai Lee, J. Y. Lee, “Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries”, KSCE Journal of Civil Engineering, Vol. 12, No. 6, pp. 367-377, 2008 DOI: https://doi.org/10.1007/s12205-008-0367-7

S. A. Assaf, S. Al-Hejji, “Causes of delay in large construction projects”, International Journal of Project Management, Vol. 24, No. 4, pp. 349-357. 2006 DOI: https://doi.org/10.1016/j.ijproman.2005.11.010

WAPDA, Kurram Tangi Dam Project, available at: http://www.wapda.gov.pk/index.php/projects/water-sector/future/

kurram-tangi-dam

WAPDA, Diamer Bhasha Dam, available at: http://www.wapda.gov.pk/index.php/projects/hydro-power/on-going/

diamer-basha-dam

Cousins Business Law, 5 methods for resolving construction disputes, available at: https://www.business-lawfirm.co.uk/blog/5-methods-for-resolving-construction-disputes.aspx

H. Armesh, H. Salarzehi, N. Mohammad, “Causes of inflation in the Iranian economy”, International Review of Business Research Papers, Vol. 6, No. 3, pp. 30-44. 2010

Indexmundi.com Iran Inflation rate (consumer prices) - Economy. 2012.

Downloads

How to Cite

[1]
Mirzai Matin, D. 2016. Identifying The Effective Factors for Cost Overrun and Time Delay in Water Construction Projects. Engineering, Technology & Applied Science Research. 6, 4 (Aug. 2016), 1062–1066. DOI:https://doi.org/10.48084/etasr.706.

Metrics

Abstract Views: 1457
PDF Downloads: 1632

Metrics Information