Identifying The Effective Factors for Cost Overrun and Time Delay in Water Construction Projects
Abstract
Water construction projects in Iran frequently face problems which cause cost overrun and time delay, the two most common issues in construction projects in general. The objective of this survey is to identify and quantify these problems and thus help in avoiding them. This survey represents a collection of the most significant problems found in the literature, classified into 11 groups according to their source. The questionnaire form used contains 84 questions which were answered by random engineers who work in water construction projects. The Relative Importance Weight (RIW) method is used to weight the importance of each one of the 84 problems. The focus of this survey is on overall top ten issues which are: bureaucracy in bidding method, inflation, economical condition of the government, not enough information gathered and surveys done before design, monthly payment difficulties, material cost changes, law changes by the government, financial difficulties, mode of financing and payment for completed work and changes made by the owner. A section for each of these issues provides additional information about them. In the full text of this survey the same weighting method is used to classify the main groups, and the results show that issues related to the groups of government, owner and consultant has the most significant impact. The last part of this survey describes the point of view of the engineers who took part in this survey and the recommendations they made.
Keywords:
construction projects, water construction projects, Iran construction projects, time delay, cost overrunDownloads
References
S. O. Ogunlana, P. O. Olomolaiye, “A survey of site management practice on some selected sites in Nigeria”, Building and Environment, Vol. 24, No. 2, pp.191-196, 1989 DOI: https://doi.org/10.1016/0360-1323(89)90009-7
Y. Frimpong, Project management in developing countries: causes of delay and cost overruns in construction of groundwater projects, Masters Research Project, University of Technology, Sydney, Australia. 2000
Y. Frimpong, J. Oluwoye, L. Crawford, “Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study”. International Journal of project management, Vol. 21, No. 5, pp. 321-326, 2003 DOI: https://doi.org/10.1016/S0263-7863(02)00055-8
M. I. Al-Khalil, A. A. Mohammed "Delay in public utility projects in Saudi Arabia." International Journal of Project Management, Vol. 17, No. 2, pp. 101-106, 1999 DOI: https://doi.org/10.1016/S0263-7863(98)00020-9
L. Le-Hoai, Y. Dai Lee, J. Y. Lee, “Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries”, KSCE Journal of Civil Engineering, Vol. 12, No. 6, pp. 367-377, 2008 DOI: https://doi.org/10.1007/s12205-008-0367-7
S. A. Assaf, S. Al-Hejji, “Causes of delay in large construction projects”, International Journal of Project Management, Vol. 24, No. 4, pp. 349-357. 2006 DOI: https://doi.org/10.1016/j.ijproman.2005.11.010
WAPDA, Kurram Tangi Dam Project, available at: http://www.wapda.gov.pk/index.php/projects/water-sector/future/
kurram-tangi-dam
WAPDA, Diamer Bhasha Dam, available at: http://www.wapda.gov.pk/index.php/projects/hydro-power/on-going/
diamer-basha-dam
Cousins Business Law, 5 methods for resolving construction disputes, available at: https://www.business-lawfirm.co.uk/blog/5-methods-for-resolving-construction-disputes.aspx
H. Armesh, H. Salarzehi, N. Mohammad, “Causes of inflation in the Iranian economy”, International Review of Business Research Papers, Vol. 6, No. 3, pp. 30-44. 2010
Indexmundi.com Iran Inflation rate (consumer prices) - Economy. 2012.
Downloads
How to Cite
License
Authors who publish with this journal agree to the following terms:
- Authors retain the copyright and grant the journal the right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) after its publication in ETASR with an acknowledgement of its initial publication in this journal.